The clock starts on the day the notice arrives. An Energy Commission notice under the Energy Efficiency and Conservation Act 2024 means your site must appoint a registered energy manager (REM) within 3 months. The trigger is 21,600 GJ or more of energy in 12 consecutive months (regulations 3 and 4, P.U. (A) 466/2024, read 26 Nov 2026).
Three months is short. Most of it goes on finding a manager with the right type of registration.
So the first week should settle three things: the date, the year of energy data, and where the manager will come from. This post walks through each, in the order you will need them.
What is an Energy Commission notice under the EECA?
It is the letter that starts every deadline.
An Energy Commission notice is a written notice that tells an energy consumer the Energy Efficiency and Conservation Act 2024 now applies to it. Under regulation 4(2) of the Energy Efficiency and Conservation Regulations 2024, the site must appoint a Registered Energy Manager within 3 months of the notice date, because it used 21,600 GJ or more in 12 months.
The Act calls a covered site an energy consumer. That is a person who, for an activity, business or trade, is supplied with energy or energy resources and consumes them (section 2 of the Act).
The Act applies when that use, over 12 consecutive months, equals or exceeds the threshold the Minister sets (section 3(1)(a)). The regulations set the threshold at 21,600 GJ (regulation 3, gazetted 31 December 2024).
The Act came into force on 1 January 2025. It applies to Peninsular Malaysia and the Federal Territory of Labuan (section 1(3)). Sabah has its own rules, kept by the Energy Commission of Sabah.
What the notice does not mean
The notice is not a fine and not a finding that you broke the law. It is the start of a set of duties.
You break the law only if you then miss them. The fines come later, and only on conviction. They are covered further down.
Why the date on the letter matters more than the day it arrived
Every duty counts from the date printed on the notice, or from the day you appoint the manager. It does not count from the day the letter reached the right desk.
A notice that sits in a general mailbox for two weeks has already used two weeks of your three months. On day one, find the notice, write down its date and send a copy to whoever will run the search.
What deadlines start when the Energy Commission notice arrives?
Six dates follow from one letter.
The Energy Efficiency and Conservation Regulations 2024 set six deadlines. The REM is due within 3 months of the Energy Commission notice. The energy management system is due 1 year after the REM’s appointment. The first energy audit report is due 1 year after the notice, then every 5 years after that.
| Duty | Deadline | Source |
|---|---|---|
| Appoint an REM and notify the Commission | 3 months from the notice | Regulation 4(2) and (3) |
| Energy management system in place | 1 year from the REM’s appointment | Regulation 8 |
| First energy audit report | 1 year from the notice | Regulation 10(1)(a) |
| Later energy audit reports | Every 5 years from the last one | Regulation 10(1)(b) |
| First energy efficiency and conservation report | 30 days after the first year of the REM’s appointment | Regulation 9(a) |
| Later energy efficiency and conservation reports | Every year, 30 days after each anniversary of the appointment | Regulation 9(b) |
All six come from the regulations as published on the Commission’s EECA 2024 page (read 26 Nov 2026).
A worked example
The Commission gives its own example: a notice dated 1 January 2026 means the energy manager is due by 31 March 2026.
On the same notice, the first energy audit report is due within 1 year of 1 January 2026. If the manager is appointed on 15 March 2026, the energy management system is due within 1 year of that date. The first yearly report is then due 30 days after the first anniversary of the appointment.
Why two clocks run at once
Look closely at the table. Some dates count from the notice. Others count from the REM’s appointment.
The audit clock does not wait for the manager. If you spend the full three months finding a manager, you have nine months left for the audit. A Registered Energy Auditor needs data, site visits and time to write the report.
So put every date in a shared calendar on day one. The audit and the energy management system both take months, and both run in parallel with the search.
How do you check the 21,600 GJ figure on the notice?
Add up a year of bills yourself.
The Energy Commission’s Guidelines on Ascertaining Energy Consumer (GP/ST/No.44/2024) convert each energy type into gigajoules and add them up. Electricity counts at 0.0036 GJ per kWh, so 6,000,000 kWh a year reaches 21,600 GJ on its own. Natural gas, LPG and bought-in chilled water or steam are added on top.
Check the total even if you agree with the notice. The same number decides which type of manager you need, and the manager will ask for it.
Collect the last 12 consecutive months of:
- electricity in kWh, from every incoming meter on the site;
- natural gas, LPG or biodiesel, in the units on the invoice;
- steam or chilled water bought from a third party, if any;
- solar power you generate and use yourself.
Diesel and petrol are on neither of the Act’s two lists, so they are left out of the count.
The conversion factors
These come from Appendix A of the guideline (GP/ST/No.44/2024, amended 10 July 2026, read 26 Nov 2026), as restated in the guide to the Act:
| Energy | Factor |
|---|---|
| Electricity | 0.0036 GJ per kWh |
| Natural gas | 0.047233 GJ per m³, or 1.055 GJ per MMBtu |
| LPG | 0.045544 GJ per kg |
| Chilled water bought in | 0.01266 GJ per refrigeration ton hour |
| Steam at 10 bar | 2.7771 GJ per tonne |
| Biodiesel | 0.03564 GJ per litre |
| Solar photovoltaic | 0.0036 GJ per kWh |
The 0.0036 figure is simple. One kWh is 3.6 MJ, and 1,000 MJ is 1 GJ.
Three worked sums
Electricity only. A site that uses 500,000 kWh a month on average uses 6,000,000 kWh a year. That is 6,000,000 × 0.0036 = 21,600 GJ, right on the line.
Electricity and gas. A plant uses 4,500,000 kWh of electricity (16,200 GJ) and 120,000 m³ of natural gas (120,000 × 0.047233 = 5,667.96 GJ). The total is 21,867.96 GJ. The plant is over the line, though its electricity alone is not.
The Commission’s own example. The guideline’s Factory A used 8,323,446 kWh of electricity (29,964.41 GJ) and 17,287 MMBtu of natural gas (18,237.79 GJ) in 2025. Its total of 48,202.19 GJ is over 21,600 GJ but under 50,000 GJ.
The converter on the home page does the sum for you.
What the guideline leaves out
Some energy that passes through a site is not counted:
- energy bought to sell on or pass to others, such as power a building owner passes to tenants who control their own use;
- fuel used as a feedstock, such as ethane turned into ethylene;
- energy made from waste heat recovery;
- solar power exported to the grid.
Two plants of related companies in the same compound may be counted as one energy consumer. Plants separated by another owner’s factory stay separate.
Common mistakes with the sum
- Using one meter when the site has several incoming supplies.
- Adding diesel for generators or forklifts. It is not on either list.
- Using a calendar year when a different run of 12 consecutive months is higher.
- Forgetting district cooling, which arrives as chilled water rather than electricity.
If your own total comes out well below 21,600 GJ, write to the Commission with the figures and ask. Do not simply ignore the notice.
Which type of registered energy manager does your site need?
Your 12-month total decides it.
Regulation 5 of the Energy Efficiency and Conservation Regulations 2024 sets the type by energy use. A site using 21,600 to 50,000 GJ in 12 consecutive months may appoint a First Type REM. A site above 50,000 GJ needs a Second Type REM. Any external manager appointed under regulation 6 must be a Second Type REM.
| 12-month total | In-house manager | External manager |
|---|---|---|
| 21,600 to 50,000 GJ | First Type or Second Type REM | Second Type REM only |
| Above 50,000 GJ | Second Type REM | Second Type REM only |
On electricity alone, 50,000 GJ is about 13,890,000 kWh a year. A site that uses 14,000,000 kWh uses 50,400 GJ, so it needs a Second Type REM.
What makes someone a Second Type REM
A Second Type REM has held a First Type registration for at least one year with a valid practising certificate. The person has also passed the Second Type training and assessment (Guide on Registration of Energy Manager, May 2026, paragraph 4.9, on st.gov.my, read 26 Nov 2026).
A person who still holds a valid electrical energy manager registration from the old 2008 regime may apply to be a Second Type REM by sitting the Commission’s assessment, until that old certificate expires (regulation 14(3)). The guide on what changed from the 2008 rule explains the old regime.
Why the type matters for the search
The Second Type needs at least a year at First Type first, so allow time to find one. If your site is above 50,000 GJ, or you want an external manager, start the search in the first week.
Should you appoint an in-house or external registered energy manager?
The law prefers your own staff.
Regulation 4 of the Energy Efficiency and Conservation Regulations 2024 makes an in-house REM the default. Regulation 6 allows an external Second Type REM for up to three years from the Energy Commission notice. That external REM may act for up to seven other energy consumers, and the Commission must be told electronically.
The in-house route
The default under regulation 4 is a manager from among your own employees. One in-house REM may also act for up to seven other energy consumers that are related corporations of yours (regulation 4(4)).
So a group with several plants can share one registered person. Each plant is still its own energy consumer, with its own reports.
The external route
If nobody on staff is registered yet, regulation 6 gives a bridge:
- you may appoint a Second Type REM who is not your employee;
- the appointment can last no longer than three years from the date of the notice;
- you must notify the Commission electronically;
- that external REM may act for up to seven other energy consumers;
- when the appointment ends, you must appoint an REM from your own staff straight away.
The external route needs a Second Type REM, even if your site is under 50,000 GJ.
Using the three years well
The three years are a bridge, not a permanent answer. Many companies use them to send an engineer through the REM training, so a staff member is registered before the external appointment ends. Energy manager training explains that path.
Before you sign anyone
Check the person’s name and practising certificate on the Commission’s list of Registered Energy Managers on MySTEE. The list is linked from the Commission’s registration page (read 26 Nov 2026). Check the expiry date on the practising certificate too.
Then ask how many other sites they serve, how often they will visit and how they will hand over to your own engineer. Hiring a Registered Energy Manager lists nine questions to ask before you sign.
Not sure which type of REM your site needs? Send your 12-month total and the notice date through the enquiry form. You only need the two figures to start.
What should you prepare for the energy manager in the first week?
Hand over a full year of data.
Under the Energy Commission’s Guidelines on Functions and Duties of Registered Energy Manager, the REM collects at least 12 consecutive months of energy use from before the appointment. Have the bills, meter data, single-line diagram and a list of big users ready, so the manager can start on the energy management system due within 1 year.
The first-week pack
| Item | Why the manager needs it |
|---|---|
| The notice, with its date | Every deadline counts from it |
| 12 months of electricity bills, every meter | The baseline and the GJ total |
| 12 months of gas, LPG, steam or chilled water invoices | The rest of the GJ total |
| Meter data you hold | Where the energy goes, month by month |
| The single-line diagram | How power reaches each part of the site |
| A list of big users (chillers, compressors, boilers, furnaces) | The significant energy users |
| Production output and operating hours (factories) | Data the Commission asks for |
What the manager does with it
The REM’s duties are in section 5(2) of the Act. In the first year they include:
- setting up the energy management system with an Energy Management Committee;
- running committee meetings at least four times a year, and a management review with top management at least once a year;
- working with the Registered Energy Auditor on the first audit report;
- writing the yearly energy efficiency and conservation report and checking it against the bills.
Who does what inside your company
The facility or plant manager, the head of engineering or the sustainability lead usually runs the search. The managing director or the finance head signs an external REM.
Finance can pull the bills. Engineering can pull the single-line diagram and the list of big users. One person should own the calendar of deadlines.
Start the audit search too
The first energy audit report is a separate job, signed by a Registered Energy Auditor. It is due within 1 year of the notice, whatever date the manager starts. The Commission’s List of REA on MySTEE shows the registered auditors (read 26 Nov 2026). The energy audit explains what the auditor does.
What happens if you miss the deadline or the manager leaves?
Each missed duty is its own offence.
Under section 5(3) of the Energy Efficiency and Conservation Act 2024, an energy consumer that fails to appoint a Registered Energy Manager is liable on conviction to a fine of up to RM50,000. Regulation 7 adds a 14-day duty to tell the Energy Commission when the manager leaves, with a fine of up to RM10,000.
| Offence | Section | Fine up to |
|---|---|---|
| Not appointing a Registered Energy Manager | 5(3) | RM50,000 |
| Not putting in place an energy management system | 6(3) | RM50,000 |
| Not sending in the energy efficiency and conservation report | 7(4) | RM50,000 |
| Not appointing a Registered Energy Auditor for the audit | 8(4) | RM50,000 |
| Not sending in the energy audit report | 9(10) | RM50,000 |
| Not telling the Commission within 14 days that the manager left | regulation 7(4) | RM10,000 |
These ceilings are from the Act and the regulations, as set out in the guide to the Act (read 26 Nov 2026).
What else the Act says about offences
A prosecution needs the Public Prosecutor’s written consent (section 60). The Commission may offer to compound an offence for up to half the maximum fine (section 61).
When a company offends, its directors, managers and similar officers can be charged with it (section 62). That is a reason for the board to know the notice has arrived.
If the manager leaves later
Plan for it now. Regulation 7 gives 14 days from the day the office falls vacant to notify the Commission, and 3 months to appoint a new in-house REM.
If you cannot find an in-house replacement, an external Second Type REM is allowed only with the Commission’s written approval (regulation 7(3)). Training a second engineer early is the simplest protection.
Where can you read the rules yourself?
Every rule here is on the Commission’s site.
The Energy Commission publishes the Energy Efficiency and Conservation Act 2024, the 2024 regulations (P.U. (A) 466/2024) and its guidelines on its EECA 2024 page and legislation library. Energy consumers can write to enc@st.gov.my. Questions about registering energy managers go to rem@st.gov.my, the address the Commission gives (read 26 Nov 2026).
The pages to bookmark
- The Act, regulations and guidelines: the Commission’s EECA 2024 page.
- The legislation library: st.gov.my/about-us/legislation.
- Registration of energy managers and auditors, and the forms: st.gov.my/registration-energy-manager-auditor.
What comes after the first week
- an energy management system within 1 year of the first appointment (what the Act asks);
- the first energy audit report within 1 year of the notice, signed by a Registered Energy Auditor (the energy audit);
- the energy efficiency and conservation report 30 days after the first year.
If your site is a building rather than a plant, the Commission’s energy intensity rules may also apply. The building energy intensity label covers them.