Hiring a Registered Energy Manager under the EECA 2024

A site over the line must appoint a Registered Energy Manager within 3 months of the Energy Commission's notice, and the type it needs depends on how much energy it uses.

Energy Efficiency and Conservation Act 2024 (Act 861), section 5; Energy Efficiency and Conservation Regulations 2024, P.U.(A) 466/2024, regulations 4 to 7 · Checked 26 November 2026 · 16 min read

The clock starts when the Commission’s notice arrives.

From that day, a site that used 21,600 GJ or more of energy in 12 consecutive months has 3 months to appoint a registered energy manager (REM). It must also tell the Commission online who it is (Energy Efficiency and Conservation Regulations 2024, P.U.(A) 466/2024, regulation 4, read on st.gov.my 26 Nov 2026).

This page is for the company that has to hire one. It covers which type you need, in-house or external, what the REM does in a year, what happens if the REM leaves, and what to ask before you sign.

What is a registered energy manager in Malaysia?

A registered energy manager is a person on the Energy Commission (Suruhanjaya Tenaga) register who runs a large energy user’s compliance under the EECA 2024. Under section 25 of Act 861, nobody may do the work without registration and a valid practising certificate, with a fine of up to RM20,000.

The REM is the person the Energy Efficiency and Conservation Act 2024 (Act 861) asks for. The Act came into force on 1 January 2025 and applies to Peninsular Malaysia and the Federal Territory of Labuan (section 1(3)).

Sabah is different. Its Energy Commission of Sabah (ECoS) keeps its own Efficient Management of Electrical Energy Regulations 2024 and its own list of managers. See EMEER 2008 and the EECA for how the old and new rules fit.

Who is an “energy consumer” here?

The Act calls a company over the line an energy consumer. The line is 21,600 GJ of energy in any 12 consecutive months (regulation 3, P.U.(A) 466/2024).

The energy counted comes from the Act’s two lists. The Second Schedule lists energy: electricity, chilled water, steam and hot water. The First Schedule lists energy resources, such as coal, LNG, butane, propane, natural gas, biogas, biodiesel and the palm and wood fuels.

Natural gas, LPG and the other energy resources in the Act’s First Schedule count in GJ alongside the electricity. Diesel and petrol are on neither of the Act’s lists, so they are left out.

What a registered energy manager is not

An REM is not a certified energy manager (CEM). The CEM is a credential of the Association of Energy Engineers, a US body, and it does not put anyone on the Commission’s register. Read certified energy manager or Registered Energy Manager for the difference.

An REM is also not your energy auditor. The audit must be done by a Registered Energy Auditor, a separate registration and a separate job. See the energy audit.

Which type of registered energy manager does your site need?

It depends on your 12-month energy total.

The Energy Efficiency and Conservation Regulations 2024 set two types of REM. A site using 21,600 GJ up to 50,000 GJ in 12 consecutive months may appoint a First Type or Second Type REM. A site using more than 50,000 GJ must appoint a Second Type REM (regulation 5).

The table restates regulation 5 and regulation 6 of P.U.(A) 466/2024:

Energy used in 12 consecutive months Who you may appoint
Under 21,600 GJ No REM is required
21,600 GJ up to 50,000 GJ A First Type or a Second Type REM
More than 50,000 GJ A Second Type REM only
Any site, using an REM from outside the company A Second Type REM only, for up to 3 years

How to work out your total

For a sense of scale: 1 kWh is 3.6 MJ, so 21,600 GJ is 6,000,000 kWh of electricity a year. 50,000 GJ is about 13,890,000 kWh.

The Commission’s conversion table (Appendix A of its Guidelines on Ascertaining a Building and the Energy Intensity Performance of a Building, GP/ST/No.48/2024, read 26 Nov 2026) gives these factors:

Energy Factor
Electricity 0.0036 GJ per kWh
Natural gas 0.047233 GJ per m³
LPG 0.045544 GJ per kg
Chilled water 0.01266 GJ per refrigeration ton hour
Biodiesel 0.03564 GJ per litre

Our converter on the home page adds a year of bills for you.

Worked example 1: a factory just over the line

A factory used 4,500,000 kWh of electricity and 150,000 m³ of natural gas in 12 months. It also burned diesel in a standby generator.

  • Electricity: 4,500,000 × 0.0036 = 16,200 GJ.
  • Natural gas: 150,000 × 0.047233 = about 7,085 GJ.
  • Diesel: not counted, because it is on neither of the Act’s lists.

The total is about 23,285 GJ. The factory is over 21,600 GJ but under 50,000 GJ, so a First Type or Second Type REM on its own staff will do.

Note that electricity alone would have kept it under the line. Leaving out the gas is a common mistake.

Worked example 2: a plant over 50,000 GJ

A plant used 12,000,000 kWh of electricity and 200,000 kg of LPG in 12 months.

  • Electricity: 12,000,000 × 0.0036 = 43,200 GJ.
  • LPG: 200,000 × 0.045544 = about 9,109 GJ.

The total is about 52,309 GJ. That is more than 50,000 GJ, so the plant must appoint a Second Type REM. A First Type REM will not meet the rule, even on staff.

What makes someone Second Type?

A Second Type REM has held a First Type registration for at least 1 year with a valid practising certificate. They have also finished the Second Type training and assessment, and satisfied the Commission on the Act (regulation 14(2); Energy Commission, Guide on Registration of Energy Manager, May 2026, paragraph 4.9).

A person who still holds a valid electrical energy manager registration from the old Electricity Supply Act 1990 regime may apply to be a Second Type REM. They sit the Commission’s assessment, and the route stays open until that old certificate expires (regulation 14(3)).

When must you appoint a registered energy manager?

Within 3 months of the notice.

Under regulation 4(2) of P.U.(A) 466/2024, an energy consumer must appoint a registered energy manager within 3 months of the Energy Commission’s written notice. The Commission’s own example: a notice dated 1 January 2026 means the REM is due by 31 March 2026. Missing it can mean a fine of up to RM50,000.

The Commission’s example comes from its Compliance Timeline Example for Energy Consumer (read on st.gov.my 26 Nov 2026). The fine is in section 5(3) of Act 861.

One notice, several deadlines

The REM is only the first date. The others count from the notice or from the day you appoint the REM (P.U.(A) 466/2024, read 26 Nov 2026):

Duty Deadline Source
Appoint an REM and notify the Commission 3 months from the notice Regulation 4(2) and (3)
Energy management system in place 1 year from the REM’s first appointment Regulation 8
First energy audit report 1 year from the notice Regulation 10(1)(a)
Later energy audit reports Every 5 years Regulation 10(1)(b)
First energy efficiency and conservation report 30 days after the first year of the REM’s appointment Regulation 9(a)
Later yearly reports 30 days after each anniversary of the appointment Regulation 9(b)

Worked example: one calendar

Say the notice is dated 1 January 2026 and you appoint the REM on 15 March 2026. The dates then run like this:

  • REM appointed and the Commission told: 15 March 2026, inside the 31 March deadline.
  • First energy audit report: by 1 January 2027.
  • Energy management system in place: by 15 March 2027.
  • First yearly report: by 14 April 2027, 30 days after the first year.
  • An external REM, if you used one, can serve until 1 January 2029 at the latest.

Put all of these in a shared calendar on day one. Our post on the day the notice arrives walks through the first week.

Need a registered energy manager before your 3-month deadline? Ask for a price through the form. A year of energy bills is all you need to start.

Can you hire an external registered energy manager?

Yes, but only for a while.

Regulation 6 of P.U.(A) 466/2024 lets an energy consumer appoint an external registered energy manager for up to 3 years from the date of the Commission’s notice. The external REM must be Second Type, may serve up to 7 other energy consumers, and must be replaced by a staff REM when the 3 years end.

The default is an REM on your own staff. Regulation 4(1) says the energy consumer shall appoint an REM “among his employee”.

That in-house REM may also serve up to 7 other energy consumers that are related corporations of the company that appointed him (regulation 4(4)). This suits a group with several plants.

The external route, rule by rule

An external REM is allowed, with limits (regulation 6, P.U.(A) 466/2024):

  • the REM must be a Second Type REM, or one who qualified under regulation 14(3);
  • the appointment can run for no more than 3 years from the date of the Commission’s notice;
  • the external REM may serve up to 7 other energy consumers;
  • you must notify the Commission online of the appointment;
  • when the 3 years end, you must appoint an REM from your own employees under regulation 4.

In-house or external: side by side

In-house REM External REM
Type allowed First or Second Type, by your GJ total Second Type only
How long No limit in the Regulations Up to 3 years from the notice
Other sites served Up to 7 related corporations Up to 7 other energy consumers
Tell the Commission Yes, online Yes, online
Rule Regulation 4 Regulation 6

What the 3 years are for

Hiring from outside buys time to train someone on staff. Plan the handover from the first month.

Pick the engineer who will take over. Budget for their First Type training and registration. The Commission’s fees for a first registration are RM260 in all, and training fees are set by each training institution (Guide on Registration of Energy Manager, May 2026).

Check the timing too. A training certificate is valid for 5 years from the date the course was completed (Guide, paragraphs 4.5 and 4.10). Our post on energy manager training covers the course route.

If your site is over 50,000 GJ, remember the staff REM must be Second Type. That needs at least 1 year as a First Type REM first, so start the First Type early.

What does a registered energy manager do in a year?

The duties are set in section 5(2) of the Act.

Section 5(2) of Act 861 lists the registered energy manager’s duties: collect energy data, set up the energy management system within 1 year, run at least four committee meetings a year, work with the auditor and write the yearly report. An REM who fails in them faces a fine of up to RM20,000.

The Commission’s Guidelines on Functions and Duties of Registered Energy Manager (in force 1 January 2025, read on st.gov.my 26 Nov 2026) explain each one. In practice the first year looks like this:

  1. Collect the data. The REM gathers at least 12 consecutive months of energy use from before the appointment. They then keep collecting it for the whole term, for every energy type in the Act’s schedules.
  2. Set up the energy management system. The site must have one within 1 year of the REM’s first appointment (regulation 8). The REM helps the Energy Management Committee write the energy policy, and proposes the objectives, targets, action plan and energy indicators for top management to approve.
  3. Run the meetings. The REM arranges Energy Management Committee meetings at least four times a year, with minutes endorsed by the management representative. There is also a management review with top management at least once a year.
  4. Work with the auditor. The first energy audit report by a Registered Energy Auditor is due within 1 year of the notice, then every 5 years. The REM uses the auditor’s list of saving measures to propose the action plan and a measurement and verification plan.
  5. Write the yearly report. The REM prepares the energy efficiency and conservation report in the Commission’s format. They check its figures against the utility bills and invoices.
  6. Collect the extra data the Commission asks for. For factories, this includes production output, the number of processes and operating hours, and an inventory of the significant energy users. It also covers variables such as shutdown days, cooling degree days and occupancy.

What the REM needs from you

The REM cannot do this alone. Have these ready, because the REM and later the auditor will both ask for them:

  • 12 months of bills for every incoming electricity meter;
  • invoices for natural gas, LPG, biodiesel or other First Schedule fuels;
  • bills for steam or chilled water bought from a third party;
  • meter data and the single-line diagram of the electrical system;
  • a list of the big users, such as chillers, compressors, boilers and furnaces;
  • production records and operating hours, for a factory.

Who else is involved?

The Energy Management Committee and top management approve the policy and targets. A management representative endorses the meeting minutes.

The Registered Energy Auditor writes the audit report. If you later fund savings through a contract, an energy service company may come in too; see ESCOs and energy performance contracts.

Anyone acting as an energy manager under the Act without registration and a valid practising certificate faces a fine of up to RM20,000 (section 25).

What happens if your registered energy manager leaves?

You have 14 days to tell the Commission.

Regulation 7 of P.U.(A) 466/2024 says that when a registered energy manager leaves, the energy consumer must notify the Energy Commission within 14 days and appoint a new staff REM within 3 months. Missing the 14-day notice is an offence with a fine of up to RM10,000.

Staff move on, and the Regulations plan for it (regulation 7, P.U.(A) 466/2024):

  • notify the Commission within 14 days of the date the REM leaves the post;
  • appoint a new REM from your own staff within 3 months of that date;
  • if no one on staff can take it, you may appoint an external Second Type REM, but only with the Commission’s written approval and on its conditions.

Note the difference from the first appointment. After a departure, an external REM needs the Commission’s written approval. It is not the open 3-year bridge of regulation 6.

How to protect the site

This is a good reason to train a second engineer even when the first REM is settled. A second registered person on staff turns a 3-month scramble into a simple notice.

Keep the REM’s working files on a shared drive, not a personal laptop. The data, the committee minutes and the draft yearly report must survive a resignation.

What should you ask before hiring an external REM?

Check the register before the fee.

Before signing an external registered energy manager, check the Energy Commission’s REM list on MySTEE for their name and Second Type status, a valid practising certificate, and how many other sites they serve. Regulation 6(3) of P.U.(A) 466/2024 caps that at 7 other energy consumers.

Before you sign, ask for these, and check the answers:

  1. Their registration. The name and number, and that it appears on the Commission’s list of Registered Energy Managers on MySTEE.
  2. Their type. It must say Second Type for an external appointment.
  3. This year’s practising certificate. It is issued for 1 to 3 years at a time and needs proof of continuous development hours to renew (Guide on Registration of Energy Manager, May 2026, sections 5 and 6).
  4. How many other sites they serve. The limit is 7 other energy consumers under regulation 6(3).
  5. Time on site. How often they will visit, and who stands in when they cannot.
  6. The first-year deliverables. The energy management system, the four committee meetings, the work with the auditor and the yearly report, each with a date.
  7. What they need from you. Bills, meter data, the single-line diagram and production records, and by when.
  8. The handover. How they will train your own engineer to take over before the 3 years end.
  9. The fee. How it is set, and what it does not include, such as the audit, which is a separate Registered Energy Auditor’s job.

Common mistakes

  • Hiring a First Type REM from outside. Regulation 6 allows only a Second Type REM as an external hire.
  • Counting electricity only. Natural gas, LPG and other First Schedule fuels count too, and can push a site over 21,600 GJ or 50,000 GJ.
  • Counting diesel. Diesel and petrol are on neither of the Act’s lists, so they do not belong in the total.
  • Taking a CEM for an REM. Only the Commission’s register meets the Act.
  • Forgetting the handover. An external REM ends 3 years after the notice, not 3 years after you sign.
  • Not filing the appointment. Appointing an REM is not enough; the Commission must be told online.

Where can you check an REM and read the rules yourself?

Every rule here is on st.gov.my.

The Energy Commission publishes the Act, the 2024 Regulations and its REM guides on its EECA 2024 page, and links the list of registered energy managers and the forms from its registration page. All facts on this page were read there on 26 November 2026; questions go to rem@st.gov.my.

For the wider law, read the EECA 2024 explained. For the companies on offer, see energy management companies.

Who decides inside the company?

The facility or plant manager, the head of engineering or the sustainability lead usually runs the search. The managing director or the finance head signs an external REM.

Starting in the first week after the notice leaves time to compare two or three quotes. It also leaves time to check each REM on the register and file the appointment before the 3 months run out.

Questions

How long do we have to appoint an REM?

You have 3 months from the date of the Energy Commission's written notice, under regulation 4(2) of P.U.(A) 466/2024. The Commission's own example: a notice dated 1 January 2026 means the REM is due by 31 March 2026. Count from the date printed on the notice, not the day it reached you.

Can the REM be from outside the company?

Yes, for a limited time. Regulation 6 lets an energy consumer appoint an external REM for up to 3 years from the date of the Commission's notice. That REM must be a Second Type REM, or a former electrical energy manager who qualified under regulation 14(3). After that, the REM must come from your own staff.

Which type of REM does our site need?

A site using 21,600 to 50,000 GJ in 12 consecutive months may appoint a First Type or a Second Type REM. A site using more than 50,000 GJ must appoint a Second Type REM (regulation 5, P.U.(A) 466/2024). Any REM hired from outside your staff must be Second Type, whatever the site uses.

What is the fine for not appointing an REM?

An energy consumer that fails to appoint a Registered Energy Manager commits an offence under section 5(3) of Act 861, with a fine of up to RM50,000 on conviction. An REM who fails to carry out the duties in section 5(2) faces a fine of up to RM20,000 under section 5(4).

How do we check that an REM is registered?

The Energy Commission publishes its list of Registered Energy Managers on the MySTEE portal, linked from st.gov.my/registration-energy-manager-auditor. Check the person's name, that the type says Second Type for an external hire, and that the practising certificate is valid for this year. Questions go to rem@st.gov.my.

Get a quote

Need this done before your deadline? Ask for a price.

Goes to HARTA’s business development team. Nothing is shared beyond HARTA.

Read next

Does the Act cover my site?Who counts as an energy consumer, how the fuels add up, where the Act applies and what it asks.Certified energy manager or Registered Energy Manager?One is a US credential, the other is the Commission's register. Only one meets the Act.What changed from the 2008 electricity rule?The old electricity-only rule, the new 21,600 GJ line, old REEM certificates and Sabah's 2024 rule.The energy auditWho may sign it, the 12 parts of the report, the 80% rule and the data to have ready.ESCO contractsGuaranteed or shared savings, how savings are measured, and the 16 firms on the Commission's ESCO register.